Project 36- Approved proposal of Barapullah Phase-II Project with redevelopment of Kidwai Nagar (East) Project- Improvement of alternative routes /secondary network for Barapullah Phase-II corridor

    (1) Name of Project Barapullah Phase-II Project with redevelopment of Kidwai Nagar (East) Project- Improvement of alternative routes /secondary network for Barapullah Phase-II corridor PWD & NBCC
    (2) Name of the Agency PWD
    (3) UTTPEC Processing

    The proposal was discussed in 47thGoverning Body meeting of the UTTIPEC was held on 25.06.2014 under the Chairmanship of theHon’bleLt. L.G.of Delhi in which the Governing Body approvedthe proposalBarapullah Phase-II Project with redevelopment of Kidwai Nagar (East) Project- Improvement of alternative routes /secondary network for Barapullah Phase-II corridor PWD & NBCC

    Decision of Governing Body:
    As recommended by the Working Group, theOption-4was approved by the Governing Body along with provision of access to the NBCC/ MOUD project and integration of the Metro subway and implementation of the Multi-modal Integration Plans developed by UTTIPEC with following:

    1. A new link road along the Barapullah drain connecting East Kidwai Nagar to Tyagaraja Stadium and onwards to Aurobindo Marg.
    2. A U-turn at grade on the Barapullah Phase 2 road where it touches the Aurobindo Marg to provide link from East Kidwai Nagar to Tyagaraja Stadium side.
    3. The Loop connecting Ring Road to the Barapullah Elevated corridor Phase II for facilitating traffic from Dhaula Kuan side to enter Barapullah Phase II elevated road near Aurobindo Marg.
    (4) Copy of approved plan Click here
    (5) File No. F1(63)2012/UTTIPEC
    (6) Date of uploading of website 06.08.2015
    (7) Additional Details Chief Engineer (F-1)
    PWD, Flyover Project Zone F-1