Project No.63 Detailed Feasibility Study and geometric design for construction of ROB/RUB on railway crossing No. LC-12 (Delhi-Ambala Line) on Khera Kalan to KheraKhurd Road

    1

    Name of the Project

    Detailed Feasibility Study and geometric design for construction of ROB/RUB on railway crossing No. LC-12 (Delhi-Ambala Line) on Khera Kalan to KheraKhurd Road

    [F1(323)2018/UTTIPEC]

    2

    Name of the Agency

    Public Works Department, Govt. of Delhi

    3

    Consultant

    Dhrupad Consultants Pvt. Ltd.

    4

    Copy of Proposal

    Proposed ROB & RUB at Railway crossing No. LC-12 on Khera Kalan to Khurd Road

    Additional Area required for implementation of the Project

    5

    UTTIPEC Processing

    The project was discussed in the 61stUTTIPEC Governing Body (G.B.) meeting held on 24.12.2020 under the Chairmanship of the Hon’ble L.G. of Delhi. The observations & decisions of Governing Body meeting are as follows:

     

    Observations

    i. VC, DDA mentioned that there is a major congestion issue near a Y-shape junction adjacent to a railway crossing near FCI Godown inNarela and PWD was asked to prepare a separate proposal todecongest the same.

    ii. G.B. emphasized on the importance of ensuring pedestrian movementin infrastructure proposals.

     

    Decision

    Based on the above observation, the proposal was approved with thecondition to incorporate the provisions for adequate space for safe movementof pedestrian/ addressing the issue of walkability on this stretch.

    6

    Date of uploading the Project

    12.03.2021

    7

    Additional Details

    Rajesh Kumar Gupta

    Executive Engineer

    Flyover Project Division, F-11

    PWD, Govt. of Delhi

    MukarbaChowk, New Delhi 110033

    Ph.: 011-27691180

    E-mail: eepwddelhif11@gmail.com