DDA
Home   |   Photo Gallery   |   Suggestions   |   Newsletter   |   Sitemap   |   Contact us
Navigation Navigation Navigation
Navigation Navigation Navigation
Navigation Navigation Navigation
»  Format for Proposal Submission
»  Guideline for Road Marking
»  Project 13- ITO : Urban Renewal
»  Guidelines and Specifications for Crash Barriers, Pedestrian Railings and Dividers
»  Pedestrian Design Guidelines
»  UTTIPEC Street Design Checklist
»  Project 11- Proposal for comprehensive development of corridor ( NH- I /Road – No:50) between Mukarba Chowk to Wazirabad Chowk
»  New Project 17 for Approval - Proposal of closure of cut at Mathura road, opposite Nizamuddin
»  New Project 18 for Approval- Construction of RUB at Railway Crossing connecting Rama Road and Prem Nagar in Karol Bagh Zone
»  New Project 19 for Approval- Widening of Mehrauli Mahipalpur Road from Andheriya Mod to T-Junction with Aruna Asaf Ali Road
»  New Project 20 for Approval- Construction of Grade Separator at the Intersection of Pusa Road/Dr.K.S. Krishanan Marg and Patel Road in Karol Bagh.
»  New Project 21 for Approval- Proposed Underpass for Multilevel Under Ground Fully Automatic Car Parking Complex for High Court of Delhi.
»  Transit Oriented Development (TOD)
Navigation Navigation Navigation
Navigation Navigation Navigation
»  Traffic Advisory
»  Crackdown on illegal parking
»  Grand plan: Integrate all transport in Delhi, NCR
»  Gazette Notification dated 07.08.2009
Navigation Navigation Navigation


Project 15-Construction of RUB at level crossing adjacent to Roshnara Garden

1

Name of the Project

Construction of RUB at level crossing adjacent to Roshnara Garden

2

Name of the Agency

Municipal Corporation of Delhi

3

Consultants:   

M/s Park Projects Consultants  Pvt.Ltd  New Delhi

4

UTTIPEC Processing

RUB at Railway level crossing Roshnara Bagh (MCD) was presented in working Group-II B  meeting dated 13.11.09 with the following observations and decisions:

Decision of Working Group

      i.   There is acute constraint of space between proposed under-pass and the 'T' intersection, which does not allow a full proof solution for the traffic particularly the pedestrian/non-motorized traffic and the right turning movements on the intersection. The proposed solution is a compromise under the pressing circumstances when project authorities have decided to go ahead with the proposal.

 

     ii.    The consultant was requested to work out in detail, the alternative proposal by considering 30mt. road at  both  'U' loop  locations with the recommendations at (v) of observations part.

 

    iii.     Project Manager agreed to modify the proposal on the above lines and submit the appropriate drawings to UTTIPEC so that the same can be placed before the next Governing Body Meeting for its consideration.

 

Decision of Governing Body

The Governing Body in its meeting dated 23.12.2009 approved the scheme with the observations of WG-II-B and desired that before releasing the scheme, it may be seen by EM, DDA/Chairman WG-II-B.

5

 Copy of the approved plan:

6

For additional details

Executive Engineer
(Pr.) CLZ, MCD,
Sindhora Kalan,
Shakti Nagar,
Delhi -110007.