Project 76 -Integrated Transit Corridor Development and Street Network/ Connectivity Plan for the corridor/ influence zone between Sarai Kale Khan to IGI Airport including areas covering “Redevelopment of General Pool Residential Accommodation (GPRA)

    1.

    Name of the Project:

    Integrated Transit Corridor Development and Street Network/ Connectivity Plan for the corridor/ influence zone between Sarai Kale Khan to IGI Airport including areas covering “Redevelopment of General Pool Residential Accommodation (GPRA) colonies at Kidwai Nagar, Nauroji Nagar, Netaji Nagar, Sarojini Nagar, Mohammadpur, Thyagraj Nagar, Kasturba Nagar, Srinivaspuri and AIIMS Trauma Centre” in Delhi.

    2.

    Name of the Agency: 

    PWD

    3.

    Consultants   

    Feedback Infra Pvt. Ltd.

    4.

    Copy of Proposal 

    Plan AIIMS_Trauma_Center, East_Kidwai_Nagar, Kasturba_Nagar, Mohammadpur, Nauroji_Nagar, Sriniwashpuri, Thiyagraj_NagarLayout-1, Layout-2,  Layout-3,  Layout-4, Layout-5, Layout-6, Layout-7, Layout-8, Layout-9, Layout-10, Layout-11, Layout-12, Layout-13, Layout-14, Layout-15,  Barapullah_Extension_Composite_Plan-1, Barapullah_Extension_Composite_Plan-2, Barapullah_Extension_Composite_Plan-3,  Ring_Road_Improvement_Layout-1,  Ring_Road_Improvement_Layout-2

    5.

    UTTIPEC Processing

    The project was discussed in 77thUTTIPEC Working Group meeting under the chairmanship of Pr. Secretary, PWD held on 14.01.2020. The observations and recommendations of the Working Group –IIB meeting are as follows:

    Observations:

            i.    Traffic police raised the concern about the issue of parking near South Ext. market along the Ring Road. On this issue, consultant informed that adequate numbers of automated multi-level car parking’s are being proposed along the Ring Road to meet the parking demand.

           ii.    Representative from Automobile Association mentioned about the huge traffic jam on Ring Road at DhaulaKuan and Brar Square

          iii.    PWD informed that the matters pertaining to land acquisition are being taken up with the concerned land owning agencies.

          iv.    Chief Engineer (Flyover), PWD mentioned that this proposal was discussed in detail with IUT and UMTC as per the decision taken in the meeting held under the chairmanship of Secretary, (MoHUA) dated 20.5.2019. The observations/suggestions made in the proposal by the experts of IUT & UMTC have been incorporated. Chief Engineer, PWD also mentioned that the increased in density due to redevelopment has already been considered in the traffic study and based on which the proposal has been worked out.

           v.    Chairman Working Group II-B of UTTIPEC desired that PWD shall prepare a detailed note on the following:

          vi.    Implication of proposed vertical development along the Ring Road.

         vii.    Integration of current PWD proposal with the other measures taken by the executing agency to decongest the corridor in long term.

        viii.    Forecast of traffic volume count for the next 50 years.

          ix.    Timeframe for which the current PWD proposal will work.

           x.    Increase in population density due to redevelopment in terms of Master Plan provision should also be considered in traffic study.

          xi.    PWD will prepare traffic simulation Modal for each GPRA colonies (Kidwai Nagar, Nauroji Nagar, Netaji Nagar, Sarojini Nagar, Mohammadpur, Thyagrajnagar, Kasturba Nagar &Sriniwaspuri) including AIMS Trauma Centre. Simulation study of each colonies may take into account all the entries/ exits and abutting roads with following scenario:

         xii.    Scenario- I: Redevelopment of the sites without any traffic improvement interventions on the adjoining roads.

        xiii.    Scenario – II: Redevelopment of the sites with proposed traffic improvement on adjoining roads along with the proposed corridor improvement plan between Sarai Kale Khan to IGI Airport. 

        xiv.    Above scenarios must clearly show the clearance time during peak hour for both entry as well as exit from the colonies.

    Recommendation:

    Based on the above observations, Working Group- II B recommends the following:

            i.    PWD will submit the detailed concept note as mentioned in the above observations at the earliest to UTTIPEC to apprise the Pr. Secretary, PWD/ Chairman of WG- IIB of UTTIPEC.

           ii.    PWD will submit the proposals incorporating the above observations for uploading of the same on UTTIPEC website for seeking Community Feedback for the period of 30 days.

    5.

    File No.

    [File No. F1(325) 2018/ UTTIPEC]

    6.

    Date of uploading on

    Website

    07-02-2020
     

    7.

    Last date for Community Feedback:

    07-03-2020

    8.

    Contact

    Executive Engineer

    Flyover Project Division F-21

    Under Ring Road Flyover

    Opposite IGI Stadium Gate No. 9

    New Delhi – 110002

    Contact No. 9910747392

    Email ID – eepwddelhif121@gmail.com