New Project-47 for Community Feedback:- (i) Corridor from RUB Shalimar Bagh to Outer Ring Road and (ii) Extension of 30m ROW Master Plan Road form Outer Ring Road (Mukarba Chowk) upto Sec-19, Rohini / Sanjay Gandhi Transport Nagar.

    1. Name of Project Road Development Plan and Street Network / Connectivity Plan for the corridor and Mid-section based on traffic and feasibility studies for the corridor / network for (i) Corridor from RUB Shalimar Bagh to Outer Ring Road & (ii) Extension of 30m ROW Master Plan Road form Outer Ring Road (Mukarba Chowk) upto Sec-19, Rohini / Sanjay Gandhi Transport Nagar.
    2. Name of the Agency PWD
    3. Consultant Dhrupad Consultants Pvt. Ltd.
    4. Copy of Proposal /Presentation Click here:
    Option 1
    Option 2
    Option 3
    5. UTTPEC Processing Background:

    PWD vide letter dated 25.11.14 submitted the proposal having two parts:

    Part 1:Corridor from RUB Shalimar Bagh to Outer Ring Road.
    Part 2:Extension of 30m ROW Master Plan Road from Outer Ring Road (Mukarba Chowk) upto Sec-19, Rohini/Sanjay Gandhi Transport Nagar.

    Proposal was presented in Core Group meeting held on 16.12.14 by PWD andcertain observations were made.Further PWD vide letter dated 17.1.15 submitted the above mentioned proposal which was again discussed in UTTIPEC Core Group meeting held on 24.3.15and following were the observations:

    1. PWD presented two options of connecting the proposed box below the Outer Ring Road to the Sanjay Gandhi Transport Nagarthrough a flyover.It was decided that PWD will discuss this option with Railways & Flood & Irrigation Department before presenting it in the next Working Group-II-B meeting.
    2. A new option was suggested by PWD by connecting the proposed box below the RUB at Badli.It was decided that PWD will work out in this option for presenting it to the Working Group.
    3. Multi modal Integration proposal of Shalimar Bagh Metro Station to be integrated within the proposal.
    4. All Road developments to be proposed with full ROW as per Zonal Development Plan/ layout plan alongwith the cross section as per UTTIPEC Street Design Guidelines.
    5. Copy of the proposal to be forwarded to Delhi Traffic Police, Irrigation & Flood Control Department, Railways by PWD before presenting it in next Core Group / Working Group meeting.
    6. Subsequently, Project Manager F-13, PWD presented 3 options in WG-II-B meeting on 9.4.2015 which are as follows:

      1. Option-1 Proposed extension of 30m wide Master Plan Road till Sanjay Gandhi Transport Nagar-Proposal connects RUB Shalimar Bagh & Sanjay Gandhi Transport Nagar.
      2. Option-2 Proposed extension of 30m wide Master Plan Road till Sanjay Gandhi Transport Nagar-Proposal connects RUB Shalimar Bagh with Sanjay Gandhi Transport Nagar connecting directly with ROB Mukarba Chowk.
      3. Option-3 Proposed extension of 30m wide Master Plan Road till Sanjay Gandhi Transport Nagar-Proposal connects with Sanjay Gandhi Transport Nagar as well as Bawana road alongwith connecting Sanjay Gandhi Transport Nagar directly with RUB at Badli.

      Observations of the WG-II-B dated 9.4.2015

      Following were the observations during the meeting:

      1. It was observed that proposed push box below the Outer Ring Road alongwiththe 30m wide road in front of Shalimar Bagh along the Railway Line to be planned with full phase RoW of 30m as per approved Zonal Development Plan / layout plan.
      2. All three above options connecting RUB below the Outer Ring Road with Sanjay Gandhi Transport Nagar to be plannedafter consultation with all stakeholders i.e. Northern Railways etc.
      3. PWD to send the plans to Railways & Flood & Irrigation Department & other stakeholders before presenting it in the Governing Body.
      4. Project Manager F-13 proposed that in first phase, RUB Shalimar Bagh may be connected to Outer Ring Road after pushing 30m wide box below ROB on Outer Ring Road.In the second phase, it can be extended to Sanjay Gandhi Transport Nagar.
      5. Multi Modal Integration proposal of Shalimar Bagh, Metro Station approved by the Governing Body to be integrated within the proposal.

      Recommendation of WG-II-B dated 9.4.2015:

      Based on the above observations all three options were recommended for Governing Body.It was agreed to connect RUB Shalimar Bagh with Outer Ring Road after box pushing in Phase-I, as approved by PWD.

    6. Date of Uploading the project 31.07.2015
    7. Last date of Feedback 30.08.2015
    8. AdditionalDetails Executive Engineer, Flyover Division, F-131, PWD, Mukarba Chowk, G.T. Karnal Road, Delhi-110033 Phone no. 011-27695010 Email id: eepwddelhif131@gmail.com