New Project-46 for Community feedback:- Road Development Plan of Road No. 30

    (1) Name of Project Road Development Plan of Road No. 30.
    (2) Name of the Agency PWD
    (3) Consultant AEI International, Superior Global Infrastructure Consulting Pvt. Ltd.
    (4) Copy of Proposal /Presentation Click here:
    Drawing 1
    Drawing 2
    (5) UTTPEC Processing Background:

    Corridor Development Plan and conceptual design of all intersections and mid-sections based on detailed traffic and feasibility studies for Road No.30 (including Jwala Heri Mkt.), Paschim Vihar was discussed in Core Group meeting held on 07.10.2013 & WG-II-B meeting on 21.11.13

    Proposal

    Entire length of the Corridor is about 3.28Km and the objective is to provide a comprehensive solution addressing the need of Vehicular and Pedestrian/NMT Traffic.A comprehensive traffic circulation plan with parking proposal and conceptual design proposal had been prepared by the Consultants based on the suggestions of the Core Group for discussion in the Working Group.

    Option – 1
    1. Outer Ring Road – Jwala Heri Road Intersection :-
      Retrofitting proposal by converting the Elliptical Shape of existing Roundabout to Round shape has been proposed to provide smooth flow of traffic along Jwala Heri Road.
    2. Outer Ring Road to Ring Road Stretch of Road :-
      A conceptual design of street as per the UTTIPEC guidelines has been prepared allocating space for NMV and pedestrians all along the corridor.
    3. Parking:-
      Haphazard On-Street parking which disrupts the smooth flow of traffic at present to be removed from the road and Parking locations in nearby DDA market and other areas which have been identified primarily for Long Term Parking to be developed.Provision for Short Term On Street Parking has also been provided as part of the Street Design.Apart from this, a proposal for a bypass route connecting Ring Road to Outer Ring Road has also been proposed which will require retrofitting development as per detailed design to allow smooth flow of traffic avoiding the Jwala Heri Road.
    4. Option – 2

      To construct a tunnel under JwalaHeri Road for allowing smooth movement of through traffic which will involve disruption of traffic on this 30 m. R/W road having residential/commercial structures on both sides and the access to residences will also be affected.

      Recommendation:-

      Working Group recommended the Option-1 proposal for consideration of the Governing Body with the following observations:-

      1. Detailed design of the roads to be prepared as per the Street Guidelines and submitted as stage-II submission for approval.
      2. Long Term Parking proposals to be taken up with DDA in the Commercial Centre.
      3. Short term on Street Parking to be implemented as per the plan with the assistance of the Traffic Police for imposing penalty on vehicles on no parking area.
      4. A presentation was made to the Governing Body on 22.11.2013.

        Decision

        As recommended by the Working Group, the Option -I wasapproved in principleby the Governing Body with the above observations.

    (6) Date of Uploading the project 26.12.2014
    (7) Last date of Feedback 25.01.2015
    (8) AdditionalDetails Executive Engineer, Flyover Division, F-134, PWD, Mukarba Chowk, G.T. Karnal Road, Delhi-110033