Project 2 for Approval - Construction of 7 entry Gates on National Highways and State Highways.

    1. Name of the Project: Construction of 7 entry Gates on National Highways and State Highways.  
    2. Name of the Agency:  DSIIDC  
    3. All  plans       TIKRI BORDER -1, TIKRI BORDER -2,
      NAND_NAGARI-1, NAND_NAGARI_FINAL-2 
    LONI_ROAD-1, LONI_ROAD FINAL-2,
    GAZI PUR_FINAL(1), GAZI PUR_FINAL-2  
    4. Working Group – II- B Processing:

    This proposal was discussed in Working Group II- B meeting held on 6.01.09. Observation:
    •          DSIIDC explained that entry gates on four locations (i.e. Tigri, Loni Rd., Gazipur & Nand Nagri) are being considered as per the proposal submitted to DUAC.
      Decision:        

     Proposal be submitted with the following:-

        
    1.     Location Plan shown on the Zonal Plan
    2.      Section & elevation of the structure
    3.      Layout plan showing in detail (in appropriate scale) the location of the structure integrating with the proposed / approved road development plan.
    4.      Viability of shifting at the time of comprehensive development, if no approved road development plan is available.

            The copies of the proposal alongwith a brief report be sent to all the Working group members through e-mail/hard copy with three sets to the Convenor of the Working Group for   discussion in the next Working Group meeting.

       
    5. Give your comments/ observations (not more than 250 words) within four week  (i.e 2.4.09 to 30.4.09)