Project 1 for Approval - North South corridor connecting Gandhi Nagar to Shastri Park along Marginal Bund Road.

    1. Name of the Project: North South corridor connecting Gandhi Nagar to Shastri Park along Marginal Bund Road.
    2. Name of the Agency:  PWD
    3. Location Plan
    4. All  plans       SORT TERM IMP PLAN option LONG TERM IMP PLAN (option II)
    5. Working Group – II- B Processing:  

    This proposal was discussed in Working Group II- B meeting held on 6.01.09.

    Observation:          
    • Consultant presented short term and long term proposals. Short term proposal contains the surface level improvement plan with two roundabouts. Long term proposal contains a tunnel/underpass of 1.5 km. length in north-south direction connecting the Bund roads by an under-pass/tunnel through Rly line and G.T. Road.
      Decision:        
    •   The circulation plan for 1 km area around the proposed stretch to be workout on a plan.
    •        
    •  An alternative circulation system by proposing a one way system for the two roads with two roundabouts may be considered.
    •         
    • Continuity of interference-free footpaths and cycle tracks  along the road stretches & at intersections to be shown
    •         
    •  Provisions for segregated lanes and facilities for public transport system may be ensured during both phases
    •        
    •  Revised proposal be submitted incorporating the above observations.
    •  

      This proposal was again discussed in Working Group II- B meeting held on 03.2.11

      Decision: It was decided in the Special Task Force meeting chaired by Chief Secretary, Delhi Government, that the Marginal Bund Road is one of the BRT Corridor which will be planned & developed by DIMTS. PWD to coordinate with DIMTS accordingly for preparation of the Comprehensive Development Plan including the BRT corridor with DIMTS.